ROUNDABOUT OPENING SOON BUT WITH SAFETY FIRST
The crews working on the roundabout in Montezuma Creek are in their final throes of preparation before opening to the public. In recent months, crews have worked long hours to complete paving and permanent lane striping. Active work continues with the...
Residents of Montezuma Creek came together in an inspiring act of service to address a long-standing community concern — the deteriorating highway connecting Arizona and Utah.
Led by Miss Montezuma Creek Elementary School Princess 2024–2025 and her family, volunteers from across the area took...
The National Weather Service has issued additional information about recent tornados in San Juan County on Saturday, September 13.
The National Weather Service reported two tornadoes touched down on September 13, with one recorded by the agency to be lasting about 15 minutes and causing no damage,...
by David Boyle
News Director
A tornado in San Juan County destroyed homes and caused significant damage in the McCracken Mesa and Cahone Mesa areas on Saturday September 13.
Multiple tornado funnels and touchdowns were spotted across southern San Juan County and into Colorado as part of the storm...
Work continues on the massive $152 million road project on Highways 162 and 262.
On Highway 162, paving is completed between Aneth and the Colorado Border, while the Bluff to Montezuma Creek leg is still undergoing shoulder widening before travel lane paving resumes.
In Montezuma Creek, paving is...
Tewakeedah Rain Spirit Martin of Montezuma Creek was crowned the 2025-26 Miss Gallup Inter-Tribal Indian Ceremonial Queen on August 8. The daughter of Mabel and Kevin Martin, her mother Mabel told the Navajo Times that she is the first Navajo Utahn to be crowned at the event. Courtesy photo
The massive road project in southeast San Juan County continues to make progress. The project stretches from the start of the routes off Highway 191 all the way into Montezuma Creek and beyond to Aneth.
The project is aimed to improve safety along 53 miles of road, including lane widening,...
Off-road work continues on the project to improve Highways 162 and 262 in San Juan County.
A dryer than normal winter has allowed crews to make progress on the $152 million “Energy Corridor” project to improve Highways 162 and 262 in central San Juan County.
The Utah Department of Transportation (...
Bluff and Montezuma Creek firefighters mounted an aerial attack on October 23rd to extinguish a fire in the Aneth oil field.
Photo credit: Gary Lichtenstein
The $152 million Energy Corridor highway project is underway in southeast San Juan County. Over the next year, State Highways 261 and 262 will see significant work along the entire 35-mile length of the two state highways.
Officials state that extremely cooperative weather conditions has resulted...